Operating Procedures

It is essential that the APS75 Underground Pulling Trailer be properly set up before

operation. Using the following procedure will allow the unit to be set up in a short

period of time and yield optimum performance.

A. POSITIONING THE TRAILER & LOWER BOOM

Position the APS75 Puller within an approximate boom arm reach of the

manhole or duct bank. After trailer is positioned, lower boom arm.

NOTE: It may be necessary to payout a small amount of winch line (releasing it

from the boom) first to allow the boom to be lowered. If so please refer to Steps

C and D before proceeding.

NOTE: When operating the APS75 on a new build site or on soft

ground you will need to block the front jacks to prevent them from

sinking. Pulling the arm down until the lift cylinders cross the arm's

pivot point could result in damage to the puller during the pulling

operation or when lifting the arm for transport. An optional a-frame or

manhole adapter can reduce or eliminate these concerns.

Remove the traveling pin and carefully

lower the boom. (Figure 1). Install jacks,

and use jacks to raise arm into desired

position. (Figure 2). Now that the boom

is in place, minor adjustments in the

puller’s position can be made if

necessary for optimum working

alignment. If using the Hydraulic Arm

Control option, turn Master Switch to

*ARM position. The control valve is

mounted below the Control Panel. The

left lever controls right/left position. The

right lever controls up/down position.

B. STABILIzE TRAILER

After the APS75 is properly positioned,

place wheel chocks to prevent trailer

movement.

Figure 1. Remove Traveling Pin

Figure 2. Lower Arm and Install

jacks