14

95-8440

9.3

Mounting and Connecting Procedure
for Detector Separation
The PIRTB can be mounted to a wall or post, or it can

be suspended by the conduit if this does not result in
excessive vibration. A

3/8

inch spacer may be needed

between the termination box and the mounting surface

to allow adequate room for the sensor and calibration

accessory. The termination box should be electrically

connected to earth ground.

1. Lubricate the sensor threads with low vapor pressure

silicone grease, then install the sensor in the conduit

entry of the termination box. It should be tight to

ensure an explosion-proof installation, however, do

not

overtighten.

2. Connect the detector wires to the terminal strip in the

termination box as shown in Figures

22

and

23

.

3. Connect the cable leadwires from the FlexVu

UD

10

, Infiniti U

9500

or termination box to the same

terminals inside the separated termination box. Do

not

ground the shield at the termination box. Ground

the sensor wire shield at the transmitter end only.

4. Check the connections inside the termination box

and place the cover on the termination box.

5. If used with the Infiniti U

9500

Transmitter, mount and

wire the Infiniti U

9500

Transmitter as shown in Figure

22

and as described in the Infiniti U

9500

Instruction

Manual.

STARTUP PROCEDURE

1. Inhibit the output loads that are actuated by the

system to prevent activation of these devices.

2. Check that the detector has been wired properly.
3. Apply power to the system and allow the detector to

operate for a minimum of

2

hours, then check zero

and verify gas response. Perform a zero and span

calibration, if necessary.

NOTE

If the device is being used with a gas other than
methane, it must be calibrated with

50%

LFL of the

gas selected with the gas selection switch.

4. Place the system in normal operation by reactivating

the output loads.

NOTE 1

CONNECT THE GREEN SENSOR LEAD TO THE CHASSIS GROUND LUG

ON THE INSIDE BOTTOM OF THE STB ENCLOSURE.

NOTE 2

GROUND THE SHIELD AT THE DISPLAY UNIT END ONLY.

NOTE 3

HOUSINGS MUST BE ELECTRICALLY CONNECTED TO EARTH GROUND.

UD10

DISPLAY UNIT

POINTWATCH

DETECTOR

SEE NOTE 2

E2403

Sensor Connector

Power Supply Connector

Output Loop

Connector

MODBUS

Connector

R

ela

y Connect

or

P1

J2

J3

J4

P2

4-20 mA +

4-20 mA –

SHIELD

COM

RS485 A

RS485 B

HIGH ALARM COM

HIGH ALARM NC

HIGH ALARM NO

AUX ALARM COM

AUX ALARM NC

AUX ALARM NO

LOW ALARM COM

LOW ALARM NC

LOW ALARM NO

FAULT COM

FAULT NC

FAULT NO

24 VDC

24 VDC

+

SHIELD

24 VDC

24 VDC

+

SHIELD

SHIELD

C

ALIBR

A

TE

24 VDC

4-20 mA

24 VDC

+

P1-3

P1-2

P1-1

J2-3

J2-2

J2-1

J4-1

J4-2

J4-3

J4-4

J4-5

J4-6

J4-7

J4-8

J4-9

J4-10

J4-11

J4-12

J3-1

J3-2

J3-3

J3-4

J3-5

P2-6

P2-5

P2-4

P2-3

P2-2

P2-1

RED

YELLOW

WHITE

GREEN

SEE NO

TE 1

STB TERMINATION BOX

BLACK

Figure 23—Sensor Separation with FlexVu UD10 and PIR9400