Drive-Off/Moving Reel Set-Up and Lashing

Trailer Set-Up

Pay the cable off the top of the reel rotating toward the rear of the cable trailer. Use minimal reel braking.

Attaching the Lasher, Set-Up Chute and Cable

Attach a lashing wire clamp to the strand (see Aerial Installation/3.11) far enough from the initial pole to

accommodate a required expansion loop or equipment. Place the lasher on the strand and attach the lashing

wire to the lashing wire clamp.

Position the set-up chute in front of the lasher and attach it to the lasher with a block pusher (or shotgun). Attach

the pull line to the set-up chute or lasher.

Thread the cable through the set-up chute and place the cable in the lasher. Leave sufficient cable tail to

accommodate a loop, splice or equipment. Close the lasher gates.

The cable should move only through the chute. If the pole-line is offset from the reel, observe the cable closely as

it moves through the chute. Cable reel offset may cause the cable to drag on the reel flange and the cable in the

chute to bind.

lasher and set-up chute

are connected with a shuttle

watch set-up chute and

reel for potential binding

cable is pulled and

lashed at the same time

reel pays off

the top

Aerial Installation

3.13