A minimum of 24 inches separation is required at each pole

passed. Measure from the clamp center bolt twelve inches

from each side.

Web Removal

The web must be removed on QR products leaving a

smooth round cable for splicing. Note: Do NOT use a

knife. Prior to removing any cable, remove the web. The

web on QR can be removed the length of the separation or

2 inches beyond the shrink tube length.

Cable Transition

Attach the device to the strand with main body of

connectors installed. Make the cable transition into the

device. A minimum of 6 inches of straight cable must

be maintained behind the connector to allow for

splicing and flexing.

Cable Transition

Ripley-Cablematic MWSS-xxx

Minimum Separation at

Pole Passing

Integrated Messenger Installation

4.12

Splicing

Note: Seperation

is required to

prevent cable

cracking

When hand forming the transition into the equipment, do not exceed minimum bend specification.

Note: Start on the span side.

Note: Web removed before splicing cable