2 jack-up, 3 adjusting the internal lift-off protector, Jack-up – Rice Lake Contego-Hygienic Weigh Module Kits, Lateral Cable Outlet User Manual
Page 8: Adjusting the internal lift-off protector
Hygienic Weighing Module Contego®
Installation Manual
EN-6
Sartorius
2.3.2
Jack-up
Procedure
• Release the locknut (2).
• Turn up the screw (1) at the hex to lift the vessel.
Caution: Don't lift the vessel by more than
6 mm!
Turn the bolt until the load cell is unloaded and
can be removed together with the upper thrust
piece.
• Insert the upper thrust piece into the new load
cell.
• Insert the load cell into the mounting kit, push
the load cell cable through the cable gland and
block it; refer to Chapter 8.1.2.
• Adjust the internal lift-off protector; refer to
Chapter 2.3.3.
2.3.3
Adjusting the Internal Lift-Off Protector
Procedure
• Release the locknut (2).
• Turn the bolt (1) of the lift-off protector at the
hex (3) fully down to the stop.
• Turn the bolt back by 1…1½ revolutions
(approx. 2 mm) to adjust the spacing.