For a successful installation, a smooth level surface, so that the entire base of the machine is sup-
ported and rests on the mounting surface, is absolutely requried.

Note: Do not support the machine on only four points.

Note: Freestanding washer-extractors do not require anchoring bolts unless specified by state
or local codes. However it is always recommended that the machines be anchored.

Special care must be taken when machines are installed on an upper floor. Make sure that the floors
are designed to carry the static and dynamic loads of the machines. Further vibrations should be
taken into consideration so that the machine does not create vibrations in the building. Static and
dynamic loads on the floor or foundation are shown in the figure 5.2 on page 18. This table can
be used as reference when designing floors and foundations.

Table 5.2: Floor Load Data

Static floor load

Static pressure

Dynamic floor load

Max dynamic load

Dynamic pressure

kN

lbs

kN/m2

lbs-ft2

kN

lbs

kN

lbs

kN/m2

lbs-ft2

SI-110

15

3300

5.7

117

1.5

330

1.5

330

0.57

11.7

SI-110 TILT

17

3900

6.5

138.5

1.5

330

1.5

330

0.57

11.7

SI-135

22.3

4900

7.4

152

1.5

330

1.5

330

0.5

10.25

SI-135 TILT

24.9

5600

8.3

173.9

1.5

330

1.5

330

0.5

10.25

SI-200

26.8

5900

7.13

149

2.45

540

2.45

540

0.88

18.3

SI-200 TILT

30.25

6800

7.13

149

2.45

540

2.45

540

0.88

18.3

SI-275

47.7

10500

11.96

248

4.09

900

4.09

900

1.04

21.3

SI-275 TILT

51.3

11300

13.05

267

4.09

900

4.09

900

1.04

21.3

5.4.1

Mounting Bolt Installation

All B&C washer-extractors should be secured by the use of machinery anchor bolts. High strength
machinery anchors should be embedded in 3500 psi (24000 N/m2) reinforced concrete. For de-
tailed information regarding the machine anchor bolt, see the instructions included with the an-
chor bolts themselves. The information provided is just an example. Ensure that the concrete is
fully cured before proceeding.

Place the machine adjacent to the foundation. Do not attempt to move it by pushing on the sides.

1. Remove the wood skid by unscrewing the carriage bolts holding it to the bottom frame of

the machine.

2. Carefully place the machine over the anchor bolts. Raise and level it 1/2 inch above the floor

on four points, using spacers that can be removed.

3. Fill the spaces between the machine base and floor with machinery grout. Grout completely

under all frame members. Remove front panel and rear panel to gain access to all frame
members. Force grout under the machine base until all voids are filled.

18