3 bst implementation instruction – AERCO BMK 2000DF User Manual

Page 125

Advertising
background image

Benchmark 1500DF - 2000DF Boilers

CHAPTER 10. BOILER SEQUENCING TECHNOLOGY

OMM-0098_0A

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

Page 125 of 196

GF-144

Ph.: 800-526-0288

04/01/2014

10.3 BST Implementation Instruction

10.3.1 Option 1 - Constant Setpoint with DIRECT Wired Header Sensor

Step 1: Direct Wired Header Sensor Wiring

1. On the MASTER Unit, Connect the Header Temperature Sensor (AERCO PN 61040) to the Feed

Forward (FFWD) terminals on the P-1 Harness Via the terminal block labeled “Header Temp sensor”

in the I/O Box.


NOTES

:

The header sensor must be installed between 2 and 10 feet downstream of the LAST boiler in the

plant’s supply water header.

Shielded pair 18 - 22 AWG cable is recommended for header sensor wiring. There is no polarity to

be observed. The ground for the shield is at the “SHLD” terminal in the I/O the Box. The sensor end

of the shield must be left free and ungrounded.

Step 2: Configure ALL C-More Units

On ALL Boilers

:

1. Go to the Configuration Menu and set the BST Menu item to Enabled.

2. Go to the BST Menu and set the BST Mode item to BST Slave (for now).

On MASTER only

:

3. Go to the BST Setpoint item and enter the desired Setpoint.

4. Go to the BST Setup Menu item and set to Enabled.

5. Go to the BST Setpoint Mode item and select Constant Setpoint.

6. Go to the Head Temp Source item and select FFWD Temp.

When ALL C-More units have been configured

:

7. Go to the BST Menu of the desired Master unit and set the BST Mode item to BST MASTER.

Temp Sensor PN 61040 Header Temp Sensor I/O Box

Advertising
This manual is related to the following products: