CHAPTER 2 – INSTALLATION

Page 22 of 196

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, NY 10913

OMM-0098_0A

04/01/2014

Ph.: 800-526-0288

GF-144

2.8 GAS SUPPLY PIPING

The AERCO Benchmark Gas Components and Supply Design Guide, GF-2030 must be

consulted prior to designing or installing any gas supply piping.

NEVER USE MATCHES, CANDLES, FLAMES OR OTHER

SOURCES OF IGNITION TO CHECK FOR GAS LEAKS

.

Many of the soaps used for gas pipe leak testing are corrosive to

metals. Therefore, piping must be rinsed thoroughly with clean

water after leak checks have been completed.

NOTE

All gas piping must be arranged so that it does not interfere with

removal of any covers, inhibit service/maintenance, or restrict

access between the unit and walls, or another unit.

Benchmark 1500 and 2000 units contain a 2 inch NATURAL GAS inlet connection, and a 1 inch

PROPANE gas connection on the top of the unit, as shown in Figures 2-2 and 2-3.
Prior to installation, all pipes should be de-burred and internally cleared of any scale, metal

chips or other foreign particles. Do Not install any flexible connectors or unapproved gas

fittings. Piping must be supported from the floor, ceiling or walls only and must not be supported

by the unit.
A suitable piping compound, approved for use with natural gas, should be used. Any excess

must be wiped off to prevent clogging of components.
To avoid unit damage when pressure testing gas piping, the unit must be isolated from the gas

supply piping. At no time should the gas pressure applied to the unit exceed 14” W.C. A

thorough leak test of all external piping must be performed using a soap and water solution or

suitable equivalent. The gas piping used must meet all applicable codes.

2.8.1 Gas Supply Specifications

The gas supply input specifications to the unit for Natural Gas and Propane gas are as follows:

The maximum static pressure to the unit must not exceed 14” W.C.

The gas supply pressure to the unit must be of sufficient capacity to provide 2000 cfh while

maintaining the gas pressure at 6 inches W.C. for FM gas trains operating at maximum
capacity

.

2.8.2 Manual Gas Shutoff Valve

A manual shut-off valve must be installed in the gas supply line upstream of the boiler as shown

in Figure 2-7. Maximum allowable gas pressure to the boiler is 14” W.C.

WARNING

CAUTION