General

When not shipped as part of a control or switchgear panel, the relays are shipped in sturdy cartons to

prevent damage during transit. Immediately upon receipt of a relay, check the model and part number

against the requisition and packing list to see that they agree. Visually inspect the relay for damage that

may have occurred during shipment. If there is evidence of damage, immediately file a claim with the

carrier and notify the Regional Sales Office, or contact the Sales Representative at Basler Electric,

Highland, Illinois.
Proper operation of the relay may be confirmed by performing the operational test procedure of Section 5.

If the relay will not be installed immediately, store the relay in its original shipping carton in a moisture and

dust-free environment.

Mounting

Relay outline dimensions and panel drilling diagrams are shown in Figures 4-1 through 4-3.

Figure 4-1. Panel Drilling Diagram, FT11 Case