Section 3-2-1: venting layout, Pvtk-1), Installation – Montigo H38DF ST User Manual

Page 11

Advertising
background image

H*38DF ST Indoor Gas Fireplace

Page 11

XG0207 - 150204.1

Installation

Section 3-2: Installing a Roof Mounted Direct Vent Termination

(PVTK-1)
This section applies to installations where the direct vent termination

will be roof mounted.

Section 3-2-1: Venting Layout
Selection of components and details of venting lay out should

adhere to the following guidelines:

„

The maximum termination point is 32’ above the fireplace (NOTE:

if the maximum termination height is used, the flame pattern

may be affected).

„

The Vertical termination must be a minimum 2’ higher than where

the termination exits the roofing materials, (asphalt shingles,

cedar shakes, etc). This distance should be measured from the

high side of the roof slope where the flue flashing intersects the

roofing materials. (see Figures 10 to 10c).

„

Termination location must be a minimum 6’ from a mechanical

air inlet.

„

Termination location must be a minimum 18” from a parapet wall

„

For a more detailed diagram of allowed termination locations,

see Appendix A.

„

A maximum of two offsets (each offset is made up of 2-90°

bends) may be made for vertical vent runs.

„

Firestops must be installed as required by National & local codes.

„

Ensure all horizontal runs are supported with a minimum of 3

supports per 10’ of venting.

„

Install all roof flashing and storm collars as shown.

Figure 10. Top vent, Roof mounted termination with no offset in vent run.

Figure 10a. Top vent, Roof mounted with 1 offset (1 offset= two 90° bends).

Figure 10b. Top vent, Roof mounted with 2 offsets (1 offset= two 90° bends).

Roof mounted Terminations
The following details are some possible configurations for Roof

mounted terminations.

PVTK1 Termination

PVTK1 Termination

PVTK1 Termination

Advertising