Section 3-3: installing a wall mounted direct vent, Termination, Installation – Montigo H38DF ST User Manual

Page 13: Installing heat guards over terminations

Advertising
background image

H*38DF ST Indoor Gas Fireplace

Page 13

XG0207 - 150204.1

Installation

1

12”

2”

12”

12”

Section 3-3: Installing a Wall Mounted Direct Vent
Termination

This section applies to installations where the direct vent termi-

nation will be wall mounted.

1). Installation of Termination with built in frame

A Termination with a Built-In Frame is installed during framing of a structure.

1. Frame the termination opening to 11" x 11".
2. Install exterior sheathing to the structure framing.
3. Fasten the termination to the sheathing using a minimum of 4

screws.

MSR Frame

PTO-4 (5"/8")

Termination

PTO-4F (5"/8")

Termination

Figure 11. Installing a PTO-F termination.

Figure 11a. Installing a PTO termination with the MSR frame.

Figure 11d. Installing the VSS Vinyl Shield.

5). Installation of a termination shield for Vinyl Siding

The VSS Termination shield

is installed when the exterior of a structure

is clad with Vinyl siding. It is placed directly above, and on-center with

the termination.

2). Installation of termination frame at time of framing
Terminations with a MSR frame allow the installation of the frame prior

to installation of the termination.
1. Frame the termination opening to 12" x 12".
2. Secure the MSR Frame to the exterior sheathing of the structure.
3. Fasten the termination to the MSR Frame using a minimum of 4

screws.

Figure 11b. Installing a PTO termination with the BSR frame.

3). Installation of termination frame at time of framing in Masonry

Terminations with a BSR frame allow the installation of the frame in

masonry prior to the installation of the termination

1. Frame the BSR opening to 12" x 12".
2. Secure the BSR Frame to the exterior sheathing of the structure.

1. Frame the MOSR opening to 12" x 12".
2. Fasten the MOSR frame to the interior side of the studs, concrete,

or finished wall construction using a minimum of 4 screws.

3. Insert the termination into the MOSR frame as shown here, (from

the inside) and attach to the MOSR by installing a min. quantity of

4 bolts into the threaded nuts on the MOSR Frame.

4). Installation of termination from inside structure

A Termination with a MOSR Frame is installed from the inside of the

structure. These are commonly used in high-rise construction.

MOSR Frame

PTO-4 (5"/8")

Termination

Figure 11c. Installing a PTO termination with the MOSR frame.

BSR Frame

MTKOG (5"/8")

Installing Heat Guards over Terminations

is recommended

in installations where the termination is located within 7' feet above

grade, or above a pedestrian walkway, and may be Required by code

in Public areas.

1. Ensure that the two long mounting brackets are facing the bottom

of the termination. (See inset). This will provide more heat protection

at the top of the termination, where temperatures are highest.

2. Attach to the faceplate of the termination using four sheet metal

screws.

Figure 12. Installing a PTO termination heat guard.

11”

11”

Framing

Exterior

Sheathing

Fastening Hardware,

minimum 4-screws

Framing

Exterior

Sheathing

Fastening Hardware,

minimum 4-screws

PTO-4 (5"/8")

Termination

Framing

Exterior

Sheathing

Fastening Hardware,

minimum 4-screws

12”

12”

Fastening Hardware,

minimum 4-screws

Framing, con-

crete or other

materials

Exterior Sheath-

ing, concrete or

other materials

Exterior Vinyl

siding

PTO-4 (5"/8")

Termination

VSS Vinyl shield

Advertising
This manual is related to the following products: