Installation & Setup

4

4-1 Chapter Description and Objectives

It is the intent of this chapter to familiarize the reader with the proper site
requirements and installation procedures of the OS/OA blending system. The
information in this chapter is NOT meant to replace or supersede an established
local or company implemented procedures. It is meant to enhance them.

4-2 Site Requirements

This section describes site requirements in detail. These requirements are
broken down into mechanical mounting, electrical connections and pneumatic
connections. Since the OS/OA is available in several different mounting
arrangements, it is necessary for the reader to become familiar with the different
arrangements.

4-2-1 Mounting Configuration

The OS/OA System is available in (3) three basic mounting
arrangements. They are:

Machine Mount
Mezzanine Mount
Floor Mount

4-2-1-1 Machine Mount

In a machine mounting application of the OS/OA unit, there are
a few items to review before placement and mounting of the
blending system begins.

First, verify the machine flange dimensions match the OS flange
(if the optional pre-drilled holes were ordered). The OS can also
be equipped with an optional cast throat section with a drain
port. This will bolt under the bottom plate of the blender.

Verify that the machine throat is physically capable of
supporting the OS/OA blending system with a full load of
material and vacuum loading equipment installed.

Important!

While in operation, the OS/OA applies horizontal and

vertical pressures to the mounting flange. If there is a
question as to the mechanical stability of a mounting
flange, contact AEC/HydReclaim’s Engineering department.