7.7.8 Battery Test Setup

If Battery Test Setup is selected from the main menu, the following menu is displayed:

Battery Test Setup

1. Setup One-time Delayed Battery Test
2. Setup Monthly Battery Test
3. Setup Quarterly Battery Test
4. Cancel Pending Battery Test
5. Display Next Scheduled Battery Test
6. Return to Main Menu
Enter Selection:

This menu allows you to schedule, review schedule, or cancel pending battery tests. The

following menu is displayed when 1-3 is selected:

Enter Starting Month (1-12):

Enter Day of Week, Sunday = 1, (1-7):

Enter Week of Month (1-5):

Enter Hour of Test (0-23):

Enter Minute of Test (0-59):

NOTE

Press <ENTER> after each entry.

<CR> with no entry will return to Battery Test Setup

Menu.

Enter the information at the prompt with a carriage return to schedule the battery test.

If entry 4 is selected from the Battery Test Setup menu, you are prompted to enter “Y” to

cancel all pending tests. This selection cancels only pending tests and does not stop a test

currently in progress.

If entry 5 is selected from the Battery Test Setup menu, and if a Battery Test is scheduled,

the following menu is displayed:

Next Battery Test Scheduled

WK DAY MON HR:MN

4

FRI MAR 15:34

NOTE

Press <ENTER> to return to the Battery Test Setup Menu.

If entry 5 is selected and there are no tests scheduled, the following text appears:

No Battery Test Scheduled

Enter <CR> to return to Battery Test Setup Menu

NOTE

The UPS performs only one battery test in any 24-hour period.