1 specific connections, Specific connections, Caution – Emerson Series 610 User Manual

Page 29: Warning

Advertising
background image

Wiring Connections

25

8.1

Specific Connections

Refer to the drawings in this manual and any other drawings provided by Liebert for this installation.

Make all of the following connections:
1. AC power cables from input power source circuit breaker (RIB) to UPS Module Input. Observe

phase rotation.

2. AC power cables from bypass power source circuit breaker (BIB) to UPS Module Bypass input.

Observe phase rotation.

3. AC power cables from UPS Module Output to critical load. Observe phase rotation.

4. For battery cabinets: DC power cables and ground from battery cabinet to UPS module and

between battery cabinets. Observe polarity. When multiple conduits are used, an equal number of

positive and negative cables should be contained in each conduit.

5. For remote battery: DC power cables (and ground) from battery to Module Battery Disconnect,

and then to UPS Module DC bus. Observe polarity. DC power cables should be installed in

conduit with conductors in matched pairs (positive and negative).

6. Module Battery Disconnect control wiring to UPS module (and between battery cabinets, if

applicable).

7. Control wiring to the optional Remote Monitor Panel, if used. Selected alarm messages are also

available for customer use through a set of contacts on an optional separate terminal board.

Wiring must be run in individual separate steel conduit.

8. Emergency Power Off control wiring must be run in separate steel conduit.
9. Communications wiring for optional site monitoring or modem must be run in separate steel

conduit.

10. Power and control connections required for the Maintenance Bypass.
11. Any additional special wiring required at your site.

NOTE
If your installation includes a Maintenance Bypass Panelboard or switchboard, some or all

power cables will be terminated in these cabinets. Make sure all required wiring between the

UPS module and the optional cabinets is completed per the submittal drawings. Observe phase

rotation.

!

CAUTION

If there are line-to-neutral loads connected to the UPS output, the bypass input source must

be wye connected and have three phases plus neutral plus ground. If the specified input is not

available, an isolation transformer is required. Refer to 6.1 - Preferred Grounding

Configuration, Wye-Connected Service, 6.3 - Preferred Grounding Configuration

With Isolated Bypass and 6.4 - Alternate Grounding Configuration, Non-Isolated.
See 6.0 - Configuring Your Neutral and Ground Connections for an explanation of

proper grounding techniques.

!

CAUTION

UPS bypass and output neutral must be connected to only one common point in the UPS. This

neutral line must be grounded at the source. See 6.0 - Configuring Your Neutral and

Ground Connections.

NOTE
DC power and battery circuit breaker control cables are provided with Liebert battery cabinets

for use between multiple cabinets when bolted together. Power cables are sized for

interconnecting battery cabinets. Battery cabinets specified for bolting up to the UPS are

shipped with power cables to connect the battery cabinet system to the UPS module. Field-

supplied cabling must be provided to connect stand-alone battery cabinets to the UPS module.

Connections from the final battery cabinet to the UPS are provided in the field.

!

WARNING

Do not make any connections between battery tiers in the battery cabinet. These connections

will be made by the Liebert Global Services representative during start-up.

Advertising