Kitchen Hoods • Type I and Type II

Filler Panel Installation

1. Uncrate the hood and lay it on the floor with

protective material between the hood and the floor.

2. Bolt the filler panels together with 5/16 in. bolts

provided in the hardware package.

3. Position the filler panels to the hood back, and tack-

weld them into place.

4. To allow for ease of cleaning, caulk the external

seams with NSF Approved silicone caulk (GE
SCS1009, or its equivalent). The caulk is not
provided.

Installing the Back Supply Plenum

Installing the Supply Duct Collar

1. Find the center of the back supply plenum.

2. If the back supply plenum is

to have one opening, cut the
opening such that it is centered
at L /2 from the plenum end.
(Fig. 1)

3. If the back supply plenum is to

have two openings, cut openings
such that they are centered
at L /4 from each end of the
plenum. (Fig. 2)

4. Place the duct collar(s) over the

opening(s), fastening with screws
or tack-welds
every 4 to 6 in.
(10.16 to 15.24
cm). (Fig. 3)

Hanging the Back Supply Plenum

5. Hang the back supply plenum from the ceiling.

The back supply plenum needs to be mounted

31.25 in. (79.375 cm) above the finished floor. This
is measured from the lowest rear edge of the back
supply plenum to the finished floor.

Hang using threaded rod placed through the hanger
brackets.

6. Fasten the back supply to the wall, going through the

lower back supply wall.

These fasteners are to help maintain the location of
the back supply, and are not intended to hold the
weight of the back supply unit.

The fasteners should not interfere with the
removable air diffusers

Hood Hanging Height

The hood hanging height is critical. Hanging the hood at
the incorrect height may significantly reduce the ability
of the hood to function properly and may be in violation
of codes. The hood hanging height, typically 78 in.
(198.12 cm) above the finished floor, is given on the
UL label located on the end panel on the inside of the
hood. The hood must be hung level to operate properly.
The grease trough is pitched to drain into the grease
container.

HOOD

HOOD

HOOD

RIGHT FILLER PANEL

BOTTOM FILLER PANEL

TACK-WELDED TO
HOOD BACK

5/16 IN. X 3/4 IN. BOLTS
WITH WASHERS & NUTS

FASTENERS HOLDING THE

BACKSUPPLY TO THE WALL

31.25 INCH

CRITICAL

DIMENSION

L/2

L/2

L (MODULE LENGTH)

Fig. 1

L (MODULE LENGTH)

L/2

L/4

L/4

Fig. 2

Fig. 3

®