Installation and Commissioning

11

5.0

I

NSTALLATION

AND

C

OMMISSIONING

5.1

Preparation for Installation

To achieve good air circulation, ensure that there is no packaging material or other equipment that

could hinder or prevent air circulation in the area of the equipment, in the area of the heat exchanger,

in the air inlet or in the air outlet.

5.2

Positioning the XDK

After positioning, the XDK’s feet must be adjusted to make the cabinet vertical. When positioned the

doors must close easily.

5.2.1 Remove Recirculation Air Duct Transport Lock

The Liebert XDK is shipped without the gas pressure springs for the front and rear automatic door

openers installed. The springs should be installed according to separate instructions before the Lie-

bert XDK is connected and turned on.
After positioning, remove the transport lock screws at the sides of the recirculation air duct (see

Figure 5).
The recirculation air duct may be pulled out to remove items that fall into the heat exchanger tray.

Figure 5

Remove the transport lock screws

!

CAUTION

Risk of improper installation. Can cause equipment damage.
Before installing the unit, a number of points must be checked for safety and to ensure the

correct function of the server cabinet. Take care when performing these checks to ensure that

the unit functions correctly.

!

CAUTION

Risk of improper installation. Can cause equipment damage.
The XDK must be installed on a level surface. For this reason, check the horizontal alignment

with a spirit level prior to starting installation. The floor must be able to support a rack load

of 307 lb/ft² (1500 kg/m²) (with installed equipment per XDK).

Remove both screws