Planning the installation

23

Model 2292 & 2294 Series Getting Started Guide

3 • Hardware installation

Installation checklist

The installation checklist (see

table 3

) lists the tasks for installing a SmartNode 2292 or 2294 Series extender.

Make a copy of this checklist and mark the entries as you complete each task. For each SmartNode 2292 or
2294 Series extender, include a copy of the completed checklist in your site log.

Table 3. Installation checklist

Task

Verified by

Date

Network information available & recorded in site log

Environmental specifications verified

Site power voltages verified

Installation site pre-power check completed

Required tools available

Additional equipment available

All printed documents available

SmartWare release & build number verified

Rack, desktop, or wall mounting of chassis completed

Initial electrical connections established

ASCII terminal attached to console port

Cable length limits verified

Initial configuration performed

Initial operation verified