Sample Schedule for On-Site
Installation by Polycom Engineer

This schedule assumes that the facility has been completely prepared
for the installation and that all Base Station mounting is the Polycom
standard. For larger installations (greater than 18 Base Stations) the
schedule may be lengthened.

Day one

The Polycom field service engineer will install the system and train
and administrator. Our engineer will usually be on-site from 9 a.m. to
5 p.m. Activities will include the following:
When the Polycom engineer arrives on-site he/she will:
1. Survey site for installation.
2. Inventory equipment.
3. Set up MCU and verify operation.
4. Register, label, and verify operation of all handsets.
5. Program any feature codes required.
6. Install Base Stations and verify operation (see note below).
7. Test coverage of system and make any adjustments.
8. Install and verify modem connection.
9. Provide system administrator with coverage map.
10. Walk the site with the system administrator to show coverage.
11. Train a system administrator.

Polycom standard mounting is on 7/8” T-bar grid or on 3/4” steel
beams. All areas must be accessible with standard on-site
equipment. All other non-standard or non-accessible mounting of
the base stations should be completed by the customer prior to the
installation of the rest of the system.