Installation steps and responsibilities – Polycom SpectraLink 6300 MCU User Manual

Page 8

Advertising
background image

Facility Preparation: SpectraLink 6000 System: SpectraLink 6300 MCU

PN: 1725-36121-001_J.doc

8

Installation Steps and Responsibilities

9

Task

Description

Wire

Contractor or

Electrician

Field

Service

Engineer

Customer

Project Mgr/

Sys Admin

Site

Preparation

Required materials provided by customer

9

Prepare location and arrangement of
shelves

9

Prepare –48V power for shelves

9

Run cables to Base Stations

9

Terminate cables at Base Stations

9

Prepare and install demarc blocks

9

Program Telephone System ports

9

Connect cables from Base Stations and
phone lines to demarc blocks

9

Wire demarc blocks for Interface Modules

9

Install Shelves and Interface Modules

Survey site and check components

9

Install

shelves

9

Install junction panel

9

Connect power to shelves

9

Install cards in shelves

9

Connect junction panel

9

Connect demarc blocks to Interface
Modules

9

Install Base Stations

Install Base Stations in ceilings

9

Install Outdoor Base Stations

9

Check System Diagnostics

9

Initialize

System

9

Program Wireless Telephone features

9

Test System and Certify Site

9

Advertising