Survey Results

17

In general, once staff has completed the site plan review how much time does it take for the application to be
approved or denied by the a duly authorized body?

Less than 30 days

30 days to 60 days

Greater than 60 days

Please specify the current fees charged by your agency to complete each type of Site Plan Review

Site Plan Review

Amended or Revised Site
Plan (minor revision)

Amended or Revised Site
Plan (major revision)

Site Plan Review
associated with a
Conditional or Special Use
(minor revision)

Site Plan Review
associated with a
Conditional or Special Use
(major revision)

Site Plan Review
associated with a
Conditional or Special Use
(no reference to major or
minor revision)

Additional fees required if
additional information is
required by a reviewing
body (i.e., Planning and
Zoning Commission and/or
City Council)

Additional fees required if
the site plan had to be
resubmitted

Thank you for participating. A copy of the results will be provided to you at no cost. If you have any questions
concerning this questionnaire or future surveys, please contact me at [email protected] or (800) 728-
7805.

Thank you, Jim Halverson, HR Green, Inc