3. Installation

30

PNEG-900 Series 2000 Autoflow Fan/Heater and Control Installation Instructions

Drying Chamber High-Level Rotary Switch Installation

1. Drill a 2" diameter hole through the roof panel at the location shown in

Figure 3R on Page 28

.

See component placement

on Page 11

for proper placement in relation to fill auger.

2. Assemble 1/4" shaft to rotary switch with 1/4" coupler and rolled pins.

3. Screw 1-1/4" pipe coupler to bottom of rotary switch.

4. Insert 1-1/4" pipe through adjustable roof mount weldment. Leave 1-1/4" pipe sticking out the top of

the weldment 3" as shown in

Figure 3T

.

5. Install switch assembly through 2" hole in roof.

6. Install paddle to 1/4" shaft assembly with coupler and rolled pins.

Figure 3T