Figure 7-35 Installing the roof panels into exposed gaps
A
Lower roof panel (CTR-0265)
D
5/16-18 x 1 flange bolt with sealing washer (S-
10260)
B
Exposed gap
E
5/16 in. flange nut (S-3611)
11.When the lower panels are installed, fill in the exposed gaps between the upper panels, by installing
three additional upper roof panels (C) overlapping each upper roof panel on the right, adjusting the
upper roof panels as needed.
12.Install the flange bolts (D) and the flange nuts (E) along the ribs of each upper panel to secure them.
13.Install the flange bolts (D) and the flange nuts (E) to secure the lower roof panels and the upper roof
panels.