Grain Systems Tanks PNEG-4075G User Manual

Page 121

Advertising
background image

Chapter 7: Roof Assembly

18.Align the holes in the splice plate (J) and side cap plate (L) with the holes in the long center collar

channel (I), and install six bolts (N) and nuts (P) into the outer row of holes, working outward from the
center of the splice plate.

19.Repeat this procedure for the other side of the center cap plate (Q).

20.Locate the third hole from each end of the spice plates (J), and install four vendor lifting eyebolts (O),

NOT supplied by GSI, and nuts (P).

NOTE: Eyebolt will pass through three layers of steel: the splice plate (J), the center cap plate (Q),

and the long center collar channel (I).

21.Tighten all hardware to the recommended torque specifications. See

Bolt Torque Specifications,

page 24

.

Pneg-4075G 75 Ft Diameter 40-Series Bin

121

Advertising