4. Installation

PNEG-1894 Top Dry Chute Controller

15

Testing that the Sprocket Correctly Activates the Limit Switch

1. Field drill two (2) holes in bottom of chute position controller electrical box (A) large enough to

accommodate cables for power and Autoflow controls. Refer to wiring diagrams on

Pages 19

and 20

to feed conduit for wiring to the main power breaker and Autoflow controls.

(See Figure 4H.)

2. After wiring and before attaching the chain to the cable, test that the sprocket travels from the open

limit switch position to the close limit switch position. To test sprocket travel:

NOTE: For system to function when testing travel with the cover removed, the damper switch (B)

must be depressed.

a. Use tape to secure damper switch in the depressed position.

b. Ensure the sprocket (C) is in the open position when beginning testing. Use the manual dump

chute switch located on the main control panel to move between the open and closed positions.
Set the sprocket travel to the closed position on the Autoflow control and observe the bolts in the
sprocket (C) travel from the open (clockwise) position to the closed (counterclockwise) position
to the limit switch (D) as shown in

Figure 4H

.

Figure 4H

Ref #

Part #

Description

A

TD-101349

Chute Position Controller Electrical Box

B

Damper Switch

C

TD-101351

Sprocket

D

Limit Switch

Disconnect all power sources before attempting to connect wiring. All wiring
should be done by a certified electrician. Follow all national and local
electrical codes.

WARNING