3. Installation

22

PNEG-1745 WatchDog

Install Procedure

This installation is split into two (2) steps. Some installation is done in the lower control panel of the Vision
system at the dryer and the rest at the PC location. This manual does not cover running the wires between
the two (2) locations, as this is the customer’s responsibility. CAT5 cable is recommended by GSI.

Installation at the Dryer

The following items will be installed at the dryer location:

1. One short-haul modem w/ power supply.

2. DB25 to 3 position quick connect cable (Serial Cable #2).

3. Use cable ties and anchors when necessary.

Follow the steps listed below to install all components required at the dryer:

1. Turn OFF power to dryer and control panel.

2. Connect the 3 position quick connector of Serial Cable #2 to the “AUX SERIAL PORT” on the

Display I/O board located on the back of the touch screen. The connector is polarized so care should
be taken to plug it in correctly.

(See Figure 3S.)

Figure 3S

Aux serial port