3 commissioning, 1 scope of delivery, 2 installation – YSI IQ SensorNet TetraCon Sensor 700 IQ (SW) User Manual

Page 11: Commissioning -1, Scope of delivery -1, Installation -1, 3commissioning

Advertising
background image

TetraCon

®

700 IQ (SW)

Commissioning

3 - 1

ba76018e01

01/2012

3

Commissioning

3.1

Scope of delivery

TetraCon

®

700 IQ (SW)

The sensor is fitted with protective caps

Operating manual.

3.2

Installation

Connection cable

A sensor connection cable of the SACIQ or SACIQ SW type is required
to connect the sensor. The cable is available in different lengths.
Compared to the standard model SACIQ, the SACIQ SW sensor
connection cable is optimized regarding its corrosion resistance in
seawater and brackish water and adapted for use in conjunction with
the TetraCon

®

700 IQ SW. Information on this and other

IQ S

ENSOR

N

ET

accessories is given in the YSI catalog and on the

Internet.

Note
How to connect the SACIQ (SW) sensor connection cable to the
terminal strip of an MIQ module is described in chapter 3 I

NSTALLATION

of the IQ S

ENSOR

N

ET

system operating manual.

Are the plug

connections dry?

Before connecting the sensor and sensor connection cable, please
make sure that the plug connections are dry. If moisture gets into the
plug connections, first dry the plug connections (dab them dry or blow
them dry using compressed air).

Note
Do not suspend the sensor on the sensor connection cable. Use a
sensor holder or armature.
Information on this and other IQ S

ENSOR

N

ET

accessories is given in

the YSI catalog and on the Internet.

Advertising