System Operation & Testing

Page 3 - 5

3

A Flashing 80 Error code will be produced, and dispensing inhibited, if a dispense

is attempted when an annual test is running. This error can be cleared by pushing

the RESET-TEST touch button.

How to Start a Manual Test

Press and hold the RESET-TEST touch button down more than 5 seconds until

the Line Leak Test light

turns on. Do not hold the reset-test button down

longer than 4 seconds unless a manual test is desired.

Normal Operation – Sequence of Events / Steps

1.) Product Dispense – Begin ( dispenser: nozzle out / lever up / switch on )

a) Aborts / Cancels / Stops any line leak test that is running, and turns off the Line

Leak Test light

– or –

b) Perform a functional self-check and allow product dispensing IF okay – or –
c) Prevent dispensing (turn the pump off) IF an error or fault was detected

2.) Product Dispense – End ( dispenser: nozzle in / lever down / switch off )

After a short delay the 3.0 gph line leak test starts.

3.) The 3.0 gph Gross Hourly Test

Starts automaticallyafter every dispense and before a 0.2 gph test, or before a

0.1 gph test.

a) The 3.0 gph hourly test takes about 3 minutes of quiet-time to finish
b) The Line Leak Test light

stays on throughout this test

c) The process will begin again from

Step 1.)

when

Product is Dispensed

4.) The 0.2 gph Monthly-Compliance Test

a) Requires from 13 minutes – to – 4 hours of uninterrupted

quiet-time

to finish

The total time required to complete the monthly test depends on the specific

conditions at the site and within the line. Tests finish rather quickly when an
obvious pass or fail condition exists. Tests times are lengthened when a more

detailed analysis is required.

b) The 0.2 gph test is made up of one or more, 13-minute test-cycles.

)

c) The Line Leak Test light

stays on throughout the entire test

NOTE

NOTE