Alpha Technologies FlexNet PMR, GMR Series User Manual
Page 23
Advertising
031-239-C0-003 Rev C
23
Fig. 3-3, Top View
Fig. 3-4, Connection Points
3.0 Installation,
continued
3.1
PMR (Pole Mount) Installation, continued
3.1.2
Enclosure on Short Pole with battery vault, continued
Buried conduit for utility power,
battery cables from vault,and
node power cables (route
conduit up post and secure
to post). Actual location of
conduit to be determined on
site.
1
1
2
3
4
1
3/4" and 1/2" knockouts for
battery vault conduit or power
node cables. (4 places)
#8 AWG (min) Copper Ground
Wire to 8 foot ground rod.
Utility Input Cable
Bottom of enclosure
1
2
3
4
Advertising