3.2 GMR (Ground Mount) Installations

3.2.1 Pre-Installation

Before you can install the GMR series enclosure, you must decide on the location,
the type of mounting platform, and the connection and grounding options you will
use. Several mounting options are available for this enclosure. You can mount an
enclosure on a precast pad, pour-in-place pad using a template, or on an existing
concrete pad.

Things to consider:

Provide adequate room for service personnel to remove the doors for battery
installation and removal.

Wherever possible, select a site that is above the 100-year fl ood plain, and away
from residences.

Locate in the shade to minimize the effects of solar loading.

Locate in an area where airfl ow can be maximized.

Locate away from sprinkler systems or other sources of forced water.

Locate out of the prevailing wind to minimize the buildup of snow or accumulation
of wind-borne dust.

Avoid locating the enclosure where it will be an obstruction or will inhibit visibility.

Evaluate the soil conditions for suitability for the installation of the required
grounding system applicable to your particular installation.

Is utility power cabling run and terminated at the site?

NOTE:

The grounding method for a particular site will be dependent upon soil type, available space, local codes,
NEC (National Electric Code), and other site-specifi c characteristics.

ATTENTION:

It is the responsibility of the installer to meet the requirements of all applicable national and local codes. Alpha
Technologies assumes no responsibility or liability for failure of the installer to comply with the requirements of
all applicable local and national codes.