CAUTION!

Threaded insert terminals require the use of 3/4" (19mm) bolts. The use of 1" (25.4mm) bolts will seriously

damage the battery. The only exception is the terminal with the large spacer for the in-line fuse link. Apply

NO-OX grease on all exposed connections.

Torque all nuts and bolts to 110in-lbs (12.43N-m).

2.2.2.1 Threaded Insert Terminals

Fig. 2-7, Battery Terminal Bolt Stack-up

Fig. 2-8, Fuse Bolt Stack-up

2.0

Installation, continued

3/4" (19mm) x 1/4-20 Bolt

3/4" (19mm) x 1/4-20 Bolt

Battery Sense

Cable or PTS

Battery Terminal

1/4-20 Nut

Split Washer

Split Washer

Flat Washer

Flat Washer

Battery Cable

Battery Cable

Flat Washer

Spacer

Fuse

2.2.3 120/240V Configuration Procedure

This procedure is for the XM3-918D-HP only.

NOTE:

Procedure:

1. Remove the Inverter Module to access the Transformer Harness (see Fig. 2-9).

2. Connect the appropriate connector to the Transformer Harness. For the 120V

configuration, connect the end with two wires. For the 240V configuration, connect the end

with only one wire (see Fig. 2-10).

Fig. 2-9, Transformer Harness

Fig. 2-10, 120/240V Connector

120V

240V

p/n 744-281-20

p/n 744-281-21