STAGE 3

COMMISSIONING THE CONTROL PANEL

3.1 - Initial Wiring & Control Panel Setup

ZA4

1.

CONNECT POWER TERMINALS L1 - L2
AND A SUITABLE EARTH (L2 BEING LIVE!)

2.

SELECT THE MOTOR POWER SETTING ON

THE TRANSFORMER TO LEVEL 1 FOR

COMMISSIONING

3.

INSERT THE ‘START-UP’ CAPACITORS INTO

THE CONTROL PANEL. THE TWO BLACK

WIRES FOR MOTOR 1 AND THE

TWO RED

WIRES FOR MOTOR 2.

4.

ENSURE THAT THE MOTORS ARE
ADEQUATELY EARTHED.