INSTALLATION

RLN-IOM-2012-1205

SECTION 2

2-14

!

WARNING

All information in this manual is for
reference and guidance purposes,
and does not substitute for required
professional training, conduct,
and strict adherence to applicable
jurisdictional/professional codes and
regulations.

Do not store or use gasoline or other
fl ammable vapors and liquids or
corrosive materials in the vicinity of
this or any other appliances. Cements
for plastic pipe should be kept away
from all sources of ignition. Proper
ventilation should be maintained to
reduce the hazard and to minimize
breathing of cement vapors.

An uninterruptible water supply is
required and shall be connected to
the ¼” compression fi tting on the
condensate drain. The water supply
maintains a water level in the drain
kit to prevent accidental fl ue gas
emission into the boiler room.

Detail A

(Condensate Drain Kit)

BACK VIEW

For multiple boiler installation, maintain a

minimum pipe size of 1” for the header piping.

(8boilers maximum per drain kit)

5

1

/

2

Minimum

2. An uninterruptible water supply is required and shall be connected to the

1/4” compression fi tting on the drain fl oat. The water supply maintains a
water level in the drain kit to prevent the fl ue gas from entering the boiler
room through the condensate connection.

3. The 1 1/2” connection shall be piped to an appropriate drain for disposal. If

the water supply must be temporarily disconnected, the boiler(s) must be
turned off to prevent accidental fl ue gas emission into the boiler room.

4. The cover should be kept on at all times, except during maintenance of

the drain. This drain should be monitored and checked regularly in your
Reliance maintenance schedule.

5. If the water supply must be temporarily disconnected, the boilers must be

turned off to prevent accidental fl ue gas emission into the boiler room.

6. The condensate drain cover must be kept on at all times, except during

maintenance of the drain. This drain should be checked regularly in your
boiler maintenance schedule.

7. A condensate collecting tank and condensate pump will be required if a

fl oor drain is not available to collect condensate (collecting tank and pump
are not supplied with the boiler).

8. All piping (Figure 9) must be galvanized, or stainless steel and should

be free of leaks. Copper, carbon steel/iron pipe, PVC or CPVC are not
acceptable.

9. Connect 3/4” condensate drain(s) to the 1” header connected in a manifold

as shown in Figure 10. The header must be at least 5 1/2” below the

FIGURE 8 - OPTIONAL CONDENSATE DRAIN KIT