Section 2: Installation

OVERALL STEPS

A. Foundation check, layout, and base plate setting

B. Preparing tools, materials, documentation and renting a crane.

C. Setting up the modules

D. Setting the modules on load cells.

E. Wiring

F. Calibrating and Testing

Tools, Equipment and Materials

Certified Prints

A mobile crane of sufficient lifting capacity to safely lift and place the main beams
which are approximately 2000 lbs.

Four equal length twenty foot (4-20 ft.) lifting chains or cables with hooks.

IMPORTANT NOTE:

The installer MUST reserve Crane and Chains/Cables in

advance from a local rental service company.

Hand tools.

Hydraulic jacks.

 Two fifteen ton (15 ton) hydraulic

jacks.

100' steel tape measure.

String line or chalk line (both)

Pry bars.

MUST reserve a Crane in advance