Section 2: Installation

04/12

15

51173 Rev. 8

SITE PREPARATION, CONTINUED

5. Remove forms and backfill for proper drainage. A slope away from the scale

is recommended.

 Allow concrete to cure for 28 days or until a test cylinder indicates the

concrete has reached its design strength before allowing traffic on the scale.

MODULE ASSEMBLY

The Tracker scale is shipped as a bundle of steel beams and hardware that are
ready to be assembled on the jobsite.

Lay Out the Foundation

1. Determine the centerline of the foundation and mark that line along the length of

the scale with a chalk line.

2. Measure from the centerline to establish the centerlines of the load cells and the

centerlines of the anchor locations. Mark these along the length of the scale with
a chalk line as well. Reference the certified print for load cell locations and anchor
locations.

3. Place base plates into approximate locations. Have locating tools and shoring

timbers ready at each location. Load cell assemblies will be moved into final
position only after the deck concrete is cured.

Figure 2-1