D. foundation, Foundation, Only – Fairbanks Trident Precast Concrete Deck Truck Scale User Manual

Page 14

Advertising
background image

Section 3: Scale Installation

04/11

14

51255 Rev. 2

D.

Foundation

Before installing any part of the scale, the foundation must be checked for accuracy

using Foundation Inspection, Field Check List, FF-2267 / 101732 (see Appendix I).

a. Layout and position the base plates in the proper locations using the

Methods & Procedures and Certified prints. Each base plate must be level

and in full contact with the top of the pier. Adjustments can be made by

chipping the concrete or grouting under the base plates.

b. Re-check the locations of each base plate against the certified prints.

Insert two ½" roll pins into each lower cup for anti-rotation.

c. Grease and install the inner "O" ring in each load cell cup if they are not

already installed. On all cups, grease the large outer "O" rings, then install

one in the groove on the outside of each cup. Put a

3

/

16

" shim on the

lower cups, grease the outsides, and insert them into the base plates.

Lower cups for 5½" load cells have a pin which must be aligned between

the two roll pins in the base plate.

d. Place the upper cup with greased "O" ring on the edge of the upper

foundation next to each base plate.

e. Place the load cell locating tool next to each base plate.
A. Setting the modules - Preparing the modules for lifting

• The modules do not have integrated lifting channels. One (1) set

of lifting eye bolts (threaded eye bolts) is provided by Fairbanks.

• Thread and bolt lifting eye bolts at each corner of the module for

proper lifting.

WARNING! Lift only as shown in drawing below on

left side. NEVER with a fork lift beneath the panel!









Lift

ONLY

as shown below!

Do

NOT

lift panels with a fork lift!

Advertising