Section 3: Scale Installation

04/11

21

51255 Rev. 2

H.

Installing load cells

a. Unpack the load cells and mark each calibration certificate with the load

cell location/position.

* * W A R NING * *

Place hydraulic jacks ONLY at the CORNERS of the modules.

Hydraulic jacks must be placed on opposite sides to lift the module in a level

position. Lifting mid-span or between load cells will cause cracks in the concrete!

b. Starting at one end of the assembled platform, place hydraulic jacks at the

corners so the section can be lifted off the locating tool. Two (2) hydraulic

jacks may be required.

c. Lift the platform so the load cell locating tool can be removed from the

upper and lower bearing cups. Once removed, fill both cups with grease.

d. The bottom of the load cell has two flat sides which must be aligned with

the flats in the lower cup. Carefully lower the scale (hydraulic jacks) while

seating the bottom of the cell into the lower cup. Check the scale’s level

and height, particularly at the approaches. Use the load cell shims

provided to adjust load cell cups for correct height and to ensure that all

cells share an equal amount of the load. Center section cells will have up

to twice the dead load of end section cells.

Caution – Use eye protection!

e. Once satisfied with height and level, tighten the module-to-module bolts.

The nuts should be torque to 500 ft. lbs.

f. Load cell cables

Introduction: Cable protection on truck scales is extremely important to the

reliability of the scale. It is imperative for all cables to be installed off the

ground, and out of sight. The Trident truck scale has been designed to

accommodate this type of cable protection. Described in this section is the

manufacturer’s recommended installation procedure for installing and

protecting cables on the Trident truck scale.

Cable hangers: Behind every SSC or PPS mounting block is a cable hanger.

These cable hangers are used to hang excess load cell and interconnecting cables.