Motor/Electrical

Install the motor according to NEC requirements and local electri-
cal codes . The motor should have an overload protection circuit .

Wire the motor for counter-clockwise rotation when facing the
fan end of the motor .

CAUTION: Do not operate the pump to check rotation until

the pump is full of liquid .

Check all electrical connections with the wiring diagram on the
motor . Make sure the voltage, frequency, phase and amp draw
comply with the supply circuit .

If motor is supplied by Finish Thompson please use the following
wiring diagram:

If utilized, verify that the power monitor has been properly
installed according to the manufacturers instructions .

To verify correct rotation of the motor:

1 . Install the pump into the system .

2 . Fully open the suction and discharge valves .

3 . Allow fluid to flow into the pump . Do not allow the pump to

run dry . PTFE or ceramic bushings can’t be run dry without

damage to pump components .

4 . Jog the motor (allow it to run for 1-2 seconds) and observe

the rotation of the motor fan . Refer to the directional arrow

molded into the housing .

NOTE: A pump running backwards will pump but at a greatly
reduced flow and pressure .

Section III - Start- up and Operation

1 . This pump must be filled from a flooded suction tank (grav-

ity) or primed with liquid from an outside source . DB Series

pumps are not self-priming .

2 . Open the inlet (suction) and discharge valves completely and

allow the pump to fill with liquid .

3 . Close the discharge valve .

4 . Turn the pump on . Slowly open the discharge valve . Adjust

the flow rate and pressure by regulating the discharge valve .

Do not attempt to adjust the flow with the suction valve .

5 . Use of a power monitor is strongly recommended for pumps

with PTFE bushings . The power monitor will stop the pump

and help prevent damage if the pump should run dry .

Shutdown

Use the following procedure to shutdown the pump .

1 . Slowly close the discharge valve .
2 . Turn off the motor .
3 . Close the suction valve .

Flush Systems

CAUTION: Some fluids react with water; use compatible flush-

ing fluid .

1 . Turn off the pump .
2 . Completely close the suction and discharge valves
3 . Connect flushing fluid supply to flush inlet valve .
4 . Connect flushing fluid drain to flush drain valve .
5 . Open flushing inlet and outlet valves . Flush system until the

pump is clean .

Section IV - Maintenance

Recommended Maintenance Schedule

The recommended maintenance schedule depends upon the na-
ture of the fluid being pumped and the specific application . If the
pump is used on a clean fluid, it is recommended that the pump
be removed from service and examined after six months of op-
eration or after 2,000 hours of operation . If the pump is used on
fluids with solids, high temperatures, or in other conditions that
could cause accelerated wear, then this initial examination should
be sooner .
After the initial examination of the internal components and wear
items are measured, a specific maintenance schedule can be de-
termined . For best results, it is recommended that the pump be
removed from service annually for examination .

Section V - Disassembly

WARNING: Rotating Parts . This pump has components that

rotate while in operation . Follow local safety standards for locking
out the motor from the power supply during maintenance or service .

WARNING: Chemical Hazard . This pump is used for trans-

ferring many types of potentially dangerous chemicals . Always

5