Installation tasks, time, and items required (Continued)

TABLE 2

Installation task

Time estimate

Items required

Installing power cables and
powering on the Brocade DCX
8510-8

20 minutes

Power cables (provided in the Brocade DCX 8510-8
accessory kit).

Establishing serial connection,
logging in to Brocade DCX 8510-8,
and configuring IP addresses

20 minutes

Serial cable (provided in the accessory kit).

Workstation computer with a serial port or terminal server
port and a terminal emulator application (such as
HyperTerminal).

Ethernet IP addresses for the Brocade DCX 8510-8
chassis and for both control processor blades: total three
addresses.

Installing an Ethernet cable,
opening a Telnet session, and
configuring the Brocade DCX
8510-8 domain ID, date and time,
and additional system parameters.
Verify and back up configuration.

20 minutes

Ethernet cabling (optional) for Telnet access.

Refer to the Fabric OS Administrator's Guide.

Installing transceivers as needed

30 minutes
(longer if using
high-density port
blades)

SFP+, mSFP, and QSFP optical transceivers as needed.

Attaching fiber-optic cables, cable
ties, and cable guides

2-3 hours

Fiber-optic cables, cable ties, and cable management
comb.

Preparing for the Brocade DCX 8510-8 installation

NOTE
Read the

Caution and Danger Notices

before installation. Read

Power specifications

on page 131 to

plan for meeting power supply standards before installing the chassis. Read

Cable management

on

page 29 to plan for cable management.

The following steps are required to ensure correct installation and operation.

1. Provide a space that is 14 rack units (14U) high, 61.29 cm (24.09 in.) deep, and 43.74 cm (17.22

in.) wide. 1U is equal to 4.45 cm (1.75 in.).

Plan to install the Brocade DCX 8510-8 with the nonport side facing the air-intake aisle. The
Brocade DCX 8510-8 can be installed facing either direction, if serviceability and cooling
requirements are met.

2. Ensure that dedicated electrical branch circuits with the following characteristics are available:

NOTE
Refer to

Power specifications

on page 131 for specific requirements depending on your chassis

configuration.