Chapter 4

Installation

The P332G-ML is ready to work after you complete the installation instructions
below.

Required Tools

Make sure you have the following tools at hand before undertaking the Installation
procedures:

Philips (cross-blade) screwdriver

Site Preparation

Avaya P330 can be mounted alone or in a stack in a standard 19-inch equipment
rack in a wiring closet or equipment room. Up to 10 units can be stacked in this way.
When deciding where to position the unit, ensure that:

It is accessible and cables can be connected easily and according to the
configuration rule.

Cabling is away from sources of electrical noise such as radio transmitters,
broadcast amplifiers, power lines and fluorescent lighting fixtures.

Water or moisture cannot enter the case of the unit.

There is a free flow of air around the unit and that the vents in the sides of the
case are not blocked.

Note:

Use Octaplane cables to interconnect with other switches.

The environmental conditions match the requirements listed below:

Table 4.1

Environmental Prerequisites

Operating Temp.

-5 to 50°C (23 to 122°F)

Relative Humidity

5% to 95% non-condensing