1. Fold heat tape in half and wrap on itself 3 times.

2. Locate heat tape between sides of condensate trap back.

(See Fig. 42.)

3. Use wire ties to secure heat tape in place. Wire ties can be

positioned in notches of condensate trap sides. (See Fig.
42.)

4. Wrap field drain pipe with remaining heat tape, approxi-

mately 1 wrap per ft.

5. When using field-supplied heat tape, follow heat tape

manufacturer’s instructions for all other installation guide-
lines.

SEQUENCE OF OPERATION

CAUTION:

Furnace control must be grounded for

proper operation, or control will lock out. Control is
grounded through green wire routed to gas valve and
burner box screw.

Using schematic diagram, follow sequence of operation through
different modes. (See Fig. 24.) Read and follow wiring diagram
carefully.

NOTE:

If 115-v power supply to furnace or blower access panel

switch is interrupted during a call for heat, blower operates for 90
sec when power is restored before heating cycle is resumed.

I.

HEATING MODE

When wall thermostat calls for heat, R-W circuit closes. Furnace
control performs a self-check, verifies pressure switch contacts are
open, and starts inducer motor.

1. Prepurge period—As inducer motor comes up to speed,

pressure switch contacts close to begin a 15-sec prepurge
period.

2. Ignitor warm up—At end of prepurge period, ignitor is

energized for a 17-sec ignitor warm-up period.

3. Ignition sequence—When ignitor warm-up period is com-

pleted, gas valve opens, permitting gas flow to burners
where it is ignited. After 5 sec, ignitor is de-energized and
a 2-sec flame-sensing period begins.
HUM terminal on control center is energized with gas
valve. See Accessories — Humidifier section.

4. Flame sensing—When burner flame is sensed, control

begins blower on delay period and continues holding gas
valve open.
If burner flame is not sensed, control center de-energizes
gas valve and ignition sequence is repeated.

NOTE:

Ignition sequence repeats 3 additional times before a

lockout occurs. Lockout automatically resets after 3 hr or can be
manually reset by turning off 115v (not at thermostat) for 3 sec
minimum, then turning it on again.

5. Blower on delay—Sixty sec after burner flame is proven

(40 sec if jumper has been cut for 140 size unit in downflow
orientation), blower motor is energized on heating speed.
Simultaneously, electronic air cleaner terminal EAC-1 is
energized.

Fig. 41—Example of Field Drain Attachment

A94054

OPEN STAND

PIPE FOR

A/C OR

HUMIDIFIER

DRAIN

TEE

TO OPEN
DRAIN

CAUTION:

Unit must not be installed, operated, and

then turned off and left in an unoccupied structure during
cold weather when temperature drops to 32°F and below
unless drain trap and drain line have adequate freeze
protection. See Service and Maintenance Instructions for
winterizing procedure.

A93058

32

°

F MINIMUM INSTALLED

AMBIENT OR FREEZE
PROTECTION REQUIRED

Fig. 42—Condensate Trap Heat Tape

A93036

CONDENSATE TRAP

WIRE TIE(S)

HEAT TAPE

(3 WRAPS MINIMUM)

—31—