2 engine installation, Engine installation – Lull 944E-42 Service Manual User Manual

Page 113

Advertising
background image

7-11

944E-42

Engine

31. Connect a suitable engine hoist to the front engine

lift bracket (11) and the transmission lifting bracket
(10).

32. Remove the two elastic locknuts, washers, lower half

isolators and capscrews securing the engine mounts
to the frame (front).

33. Remove the two elastic locknuts and washers

securing the transmission mount to the frame (rear).

34. Carefully lift the engine/transmission assembly out

and away from the machine

35. Place engine on ground supports or a suitable

engine stand.

36. Remove the transmission mounting bracket.

37. If required, the transmission can now be separated

from the engine. Refer to Section 6.4.1,
“Transmission Removal.”

7.9.2

Engine Installation

Note: The engine harness is routed and attached at
various places on the engine using hold-down clamps
and plastic wire ties. Before installing engine and with
the help of an assistant, ensure that the engine clears
the harness during installation.

1. Attach the transmission, if removed, to the engine.

Refer to Section 6.4.3, “Transmission Installation.”

2. If removed during engine work, install the front and

rear engine mounts. Torque the FRONT (1)
mounting bolts to 44-78 lb-ft (59-106 Nm). Torque
the REAR (2) mounting bolts to 107-192 lb-ft
(145-260 Nm).

3. Attach a lifting strap or chain to the engine lift

brackets, and lift the engine clear of the ground.

4. Install two Grade 8, 5/8-11 x 3-3/4 in. capscrews (3)

down through each upper half isolators.

5. Carefully install the engine, guiding the mounting

bolts through the engine frame mounting holes.

6. Install the two bottom half isolators, rebound

washers and new elastic locknuts.Torque to
106-191 lb-ft (144-259 Nm).

7. Align the rear transmission mounts to the

transmission mounting plate (2).

8. Install two Grade 8, 5/8-11 x 3-3/4 in. capscrews and

washers (4) up through each lower half isolators and
transmission mounting plate (2).

9. Install the two washers and new elastic

locknuts.Torque to 106-191 lb-ft (144-259 Nm).

10. Remove the hoist from the lifting brackets. Remove

the lifting hook from the transmission.

11. Install the engine-to-transmission drive shaft. Refer

to Section 5.4.5, “Drive Shaft Installation.”

12. Install the engine oil filter assembly.

13. Uncap and connect and the engine oil filter inlet

hose at the engine.

14. Uncap and connect the engine oil filter return hose

from the engine.

15. Uncap and connect the previously labeled fuel return

line to the injector pump.

16. Uncap and connect the previously labeled fuel inlet

line to the fuel lift pump.

17. Connect the previously labeled electrical wire

connections on the engine.

18. Uncap and connect the previously labeled heater

hoses to the engine (if equipped).

19. Install the reservoir retainer assembly and battery

tray.

20. Uncap and connect previously labeled transmission

hoses.

21. Install the hydraulic reservoir.

22. Install the complete radiator assembly. Refer to

Section 7.4.2, “Radiator/Oil Cooler and
Replacement.”

Note: Use new oiled o-rings as required. ALWAYS
replace seals, o-rings, gaskets, etc., with new parts to
help ensure proper sealing and operation. Lubricate
seals and o-rings with clean hydraulic oil.

MU7420

1

2

3

4

4

Advertising