1. Install thrust washer (29) in spindle (60).
2. Install o-ring (19) into groove of support ring (6).
3. Install planet gears (1) onto planet pins which are

part of spindle (60).

4. Install snap rings (15) on planet pins of spindle (60)

in order to fix the planet gears (1).

5. Put ring gear (30) onto support ring (6) and fix ring

gear (30) with hex head bolts (23). Tighten bolts with
torque wrench to 15.5 ft. lbs.(21.1 Nm).

6. Insert the first stage planetary assembly (7) into

drive.

7. Install o-ring (33) in groove of ring gear (30).
8. Install end the cover unit (8) on shoulder ring gear

(30) and fix with snap ring (34).

9. Install seal rings (21) and screw plugs (22).

10. Before installation of motor, CHECK THAT THERE IS

1-2mm OF CLEARANCE BETWEEN THE MOTOR
SPLINE SHAFT SHOULDER AND THE COUPLER
(62).

11. Install the motor and reconnect hydraulic lines.
12. Roll motor so that one fill plug is at 12 o’clock posi-

tion, and the other is at 3 o’clock. Fill to bottom of 3
o’ clock plug with gear oil. reinstall plugs

Initial Start-up and After Repairs

Before operating the machine, make sure that the drive is
filled with clean oil, approximately.2 us gallons(.8 L). An
accurate oil level is determined by the oil level plug, which
should be removed before oil fill.

With the gear case filled to their proper levels, start the
machine and allow sufficient time for run-in at moderate
pressure and speed before running at full speed. After 4
hours of operation, recheck oil level.

Maintenance

Daily: - Check for oil leakage

Weekly: - Check oil level

Monthly: - Check mounting bolt torque

Oil Change Interval-Gear Drive

1. Perform the first oil change after approximately 150

hours.

2. Subsequent changes, every 1500 hours or annually,

whichever occurs first.

NOTE: Flush the drive before filling with new oil.

Setting of Tapered Roller Bearings

NOTE: The numbers in parentheses ( ) reference the figure

Drive Hub- Cutaway.

1. De-grease threads of the spindle (60) and shaft nut

(4).

2. Spin the shaft nut onto spindle by hand to insure the

threads are in good condition.

3. Apply Loctite 270 evenly to threads of the shaft nut.
4. Rotate the support ring repeatedly in one direction

only, during setting of the tapered roller bearings.

5. Tighten shaft nut to 626 ft. lbs. (850 Nm).
6. Do not use the hub for 24 hours to allow the Loctite

to harden properly.

7. Do not fill with oil for 24 hours to allow the Loctite to

harden properly.

Securing of the Shaft Nut

1. After proper bearing setting is completed, use a suit-

able punch to place ball (24) 0.04 to 0.05 inches (1.1
to 1.3 mm) into the spindle thread. Then set ball (24)
in position by punching in expander (25).