10 tie down and lifting, Tie down, Lifting – JLG 150HAX Operator Manual User Manual

Page 63: 11 towing, 10 tie down and lifting -11, Tie down -11 lifting -11, 11 towing -11

Advertising
background image

SECTION 4 - MACHINE OPERATION

3121213

– JLG Lift –

4-11

4.10 TIE DOWN AND LIFTING

Tie Down

When transporting machine, boom must be in the stowed
mode with turntable lock pin engaged and machine securely
tied down to truck or trailer deck. A lifting/tie down eye is pro-
vided at each of the four corners of the machine frame. In
addition, another four tie down eyes are provided on the
machine frame, one behind each of the four drive/steer
wheels.

Lifting

If it becomes necessary to lift the machine using an over-
head or mobile crane, it is very important that the lifting
devices are attached only to the designated lifting eyes, and
that the turntable lock pin is engaged.

A lifting/tie down eye is provided at each of the four corners
of the machine frame. When lifting the machine, each of the
four chains or slings used for lifting the machine must be
adjusted individually so the machine remains level when ele-
vated.

SECURE TURNTABLE WITH TURNTABLE LOCK BEFORE TRAVELING
LONG DISTANCES OR HAULING MACHINE ON TRUCK/TRAILER.

4.11 TOWING

The machine is not equipped with a tow package. Refer to
Section 5 for emergency towing procedures.