Chain Tension Inspection—
G9-43A/G10-43A

1. Park machine on level ground. Place transmission

control lever in (N) NEUTRAL, engage parking brake
and level boom.

2. Place a Do Not Operate Tag on both ignition key

switch and steering wheel.

3. Extend the boom 4-5 ft (1,2-1,5 m), then fully retract

the boom. Verify boom is level.

4. Measure the following three dimensions; A, B & C.

5. At the boom head, verify dimension “A” is between

17.000-17.312 in (421,8-439,7 mm).

6. At the bottom front of the boom, verify dimension “B”

is 1.500-1.512 in (38,1-38,4 mm) of the washer stack
on the retract chain clevis.

7. At the back of the boom, verify dimension “C”

3.069 in (77,9 mm) on the extend chain clevis.

Note: Belleville washers are shown in the
un-compressed state.

8. Boom adjustment will be required if the above

dimensions are not met.

3.8.4

Chain Tension Adjustment—
G9-43A/G10-43A

1. Remove extend chain lock nut (1) and loosen

adjustment nut (2) until belleville washers (3) are
free to turn on extend rod.

2. Verify the belleville washers (3) are in the correct

order as shown. Remove the extend chain
adjustment nut (2) and correct if required.