General -9, Daily walk-around inspection - sheet 2 of 3 -9, General – JLG 510AJ Series II Operator Manual User Manual
Page 29

SECTION 2 - USER RESPONSIBILITIES, MACHINE PREPARATION, AND INSPECTION
3121292
– JLG Lift –
2-9
GENERAL
Begin the "Walk-Around Inspection" at Item 1, as noted on
the diagram. Continue to the right (counterclockwise
viewed from top) checking each item in sequence for the
conditions listed in the following checklist.
TO AVOID POSSIBLE INJURY, BE SURE MACHINE POWER IS OFF.
DO NOT OPERATE MACHINE UNTIL ALL MALFUNCTIONS HAVE BEEN
CORRECTED.
INSPECTION NOTE: On all components, make sure there
are no loose or missing parts, that they are securely fas-
tened, and no visible damage, leaks or excessive wear
exists in addition to any other criteria mentioned.
1. Platform Assembly and Gate - Footswitch works
properly, not modified, disabled or blocked. Gate latch,
stop, and hinges in working condition.
2. Platform & Ground Control Consoles - Switches and
levers return to neutral, decals/placards secure and
legible, control markings legible.
3. All Hydraulic Cylinders - No visible damage; pivot
pins and hydraulic hoses undamaged, not leaking.
4. Boom Sections/Uprights/Turntable - See Inspection
Note.
5. Boom Limit Switches - Switches operate properly.
6. Drive Motor, Brake, and Hub - No evidence of leak-
age.
7. Wheel/Tire Assemblies - Properly secured, no miss-
ing lug nuts. Inspect for worn tread, cuts, tears or other
discrepancies. Inspect wheels for damage and corro-
sion.
8. Hood Assemblies - See Inspection Note.
Figure 2-4. Daily Walk-Around Inspection - Sheet 2 of 3