15 air compressor, Normal startup procedure, Normal shutdown procedure – JLG 740AJ ANSI Operator Manual User Manual

Page 86: Daily operation, 15 air compressor -20, 15 air compressor normal startup procedure

Advertising
background image

SECTION 4 - MACHINE OPERATION

4-20

– JLG Lift –

3121650

4.15

AIR COMPRESSOR

Normal Startup Procedure

1.

Check compressor oil level - top up if necessary.

2.

Air service valve (beside the compressor) closed.

3.

Start the engine.

4.

Compressor switch (in the platform) ON - compressor should
activate.

5.

Allow the compressor to warm up for several minutes before
operating.

Normal Shutdown Procedure

1.

Close service valve and allow compressor to unload and cool
down (approx. 5 min.).

2.

Position the compressor switch in the platform to OFF.

3.

Shut down the engine.

Daily Operation

Before Starting:

1.

Check compressor oil level.

2.

Check for any leaks or loose bolts.

3.

Check drive belt is tight.

After Starting:

1.

Check pressure gauge for correct operating pressure.

2.

Check for leaks.

Advertising