6 commissioning and operation, 1 before switching on, 2 during operation – Lenze GPA servo planetary geared motors User Manual

Page 16: Commissioning and operation

Advertising
background image

Commissioning

Before switching on

6



16

BA 12.0030 EN 2.0

6

Commissioning and operation



Stop!

The drive may only be commissioned by skilled personnel!

6.1

Before switching on

Check:
ƒ Is the mechanical fixing o.k.?
ƒ Are the electrical connections o.k.?
ƒ Are all rotating parts and surfaces, which may become hot, protected against

contact?

6.2

During operation

ƒ During operation, check the drive periodically and take special care of:

– unusual noises or temperatures,
– leakages,
– loose fixing elements,
– the condition of the electrical cables.

ƒ If any interference should occur, proceed according to the troubleshooting list in

chapter 8. If the interference cannot be eliminated, please contact the Lenze Service.