6 commissioning, 1 before switching on, Commissioning – Lenze EMF2191IB User Manual

Page 34: Before switching on

Advertising
background image

Commissioning

Before switching on

6

l

34

EDSMF2191IB EN 2.0

6

Commissioning

During commissioning, system−dependent data as e.g. motor parameters, operating
parameters, responses and parameters for fieldbus communication are selected for the
controller.

In Lenze devices, this is done via codes. The codes are stored in numerically ascending order
in the Lenze controllers and in the plugged−in communication/function modules.

In addition to these configuration codes, there are codes for diagnosing and monitoring
the bus devices.

6.1

Before switching on

(

Stop!

Before switching on the standard device with the communication module for
the first time, check the entire wiring for completeness, short circuit and earth
fault.

Advertising