5 commissioning, 1 initial switch-on, Commissioning – Lenze EPM−H502 User Manual
Page 68: Initial switch−on
Advertising
Commissioning
Initial switch−on
5
l
68
EDBPM−H502 DE/EN/FR 5.1
5
Commissioning
5.1
Initial switch−on
Commissioning requires a complete wiring of the system bus.
Before switching on the supply voltage, check ...
ƒ
the complete wiring for completeness and short circuit,
ƒ
whether the bus system is terminated at the first and last physical node.