2 project transfer to the operating unit, 1 connecting operating unit and pc, Project transfer to the operating unit – Lenze EPM−H502 User Manual

Page 69: Connecting operating unit and pc, Commissioning, Stop

Advertising
background image

Commissioning

Project transfer to the operating unit

Connecting operating unit and PC

5

l

69

EDBPM−H502 DE/EN/FR 5.1

5.2

Project transfer to the operating unit

5.2.1

Connecting operating unit and PC

(

Stop!

Only connect PC and operating unit when the units are switched off!

l

HMI Designer

FUSE 800 mA

+(18-32) VDC 10W
0 VDC

1
2
3
4

N. C.

12

3
4

ASP8

1

2

0

N.C.

CAN+

Shield

CAN-

V-

1 2 3 4 5

h502_007

Fig. 5−1

Connecting operating unit and PC

1. Plug the programming adapter EPZ−H111

0

onto the ASP8 interface.

2. Connect download cable EPZ−H110

1

to programming adapter EPZ−H111

0

.

3. Plug download cable EPZ−H110

1

onto COM1 or COMx

2

at PC.

Advertising