Commissioning
Project transfer to the operating unit
Connecting operating unit and PC
l
69
EDBPM−H502 DE/EN/FR 5.1
5.2
Project transfer to the operating unit
5.2.1
Connecting operating unit and PC
(
Stop!
Only connect PC and operating unit when the units are switched off!
l
HMI Designer
FUSE 800 mA
+(18-32) VDC 10W
0 VDC
1
2
3
4
N. C.
12
3
4
ASP8
1
2
0
N.C.
CAN+
Shield
CAN-
V-
1 2 3 4 5
h502_007
Fig. 5−1
Connecting operating unit and PC
1. Plug the programming adapter EPZ−H111
0
onto the ASP8 interface.
2. Connect download cable EPZ−H110
1
to programming adapter EPZ−H111
0
.
3. Plug download cable EPZ−H110
1
onto COM1 or COMx
2
at PC.